Part of: Specialist Earthing

Development of detailed design HV combined heating and power plant (food industry).

A detailed substation earthing study was previously completed on site, requiring close co-operation with a regional DNO (District Network Operator) – as a result of a unique connection configuration.

PTSG Specialist Earthing and Power was contracted to develop an earthing solution for the new build CHP plant. The installation work was undertaken by a third party, with the design development requiring co-operation with other professionals.

The design was completed ensuring that both industry- and client-specific requirements were adhered to. The final testing, commissioning and certification of a compliant installation were also undertaken by PTSG.

The design documentation was produced working in collaboration with others and enabled a safe, cost-effective and deliverable solution to be achieved.

 

Electrical
Electrical Testing
Electrical4
Lightning Protection Systems
Electrical5
Lightning Protection Testing
Electrical2
Specialist Earthing
Electrical3
Surge Protection
Our Divisions